  • Contract Amount: $1,956,000
  • Location: Henderson, KY
  • Duration: 4 Months 
  • Contract Type: Plan & Spec
  • Market: Chemical
  • Owner: Mosaic
  • General Contractor: Ryan & Associates, Inc.
  • Engineer: Moody

Ryan & Associates was tasked to replace the existing small-bore carbon steel piping with stainless steel. We also replaced all “first” valves on both tanks, expansion bellows and spring cans.

To enhance functionality, new level transmitter piping and ESD valves were added. Additionally, we installed six new nozzles to the top of both tanks, which all went through the suspended deck and, new platforms to both tanks.